− | The answer depends on whether or not the Session contains assets (scenery, consists) and settings (rules, driver commands, industry and wagon loads, weather, time of day, etc) that you want to continue to use in the new merged Route and its Session. | + | The answer depends on whether or not the Session contains assets (scenery, consists) and settings (rules, driver commands, industry and wagon loads, weather, time of day, etc) that you want to continue to use in the new merged Route and its Session. If this is the case then load the Session. If the Session contains nothing that you need, then only load the Route. |
<br><br> | <br><br> | ||
Note that when you add the '''to-be-merged route''' its Route assets and data will be loaded but not any Session assets or data so this is the only opportunity you will have to load any Session assets and data. If the Session attached to the ''Base Route'' contains nothing that you need then load the Route only into Surveyor. | Note that when you add the '''to-be-merged route''' its Route assets and data will be loaded but not any Session assets or data so this is the only opportunity you will have to load any Session assets and data. If the Session attached to the ''Base Route'' contains nothing that you need then load the Route only into Surveyor. |
Revision as of 08:37, 31 October 2019
Merging Routes
The information in this Wiki Page applies to both TANE and TRS19.
Contents |
The Surveyor Merge Routes command allows two different routes to be joined together edge-to-edge or end-to-end.
Before You Start Merging
Make sure that you have backup copies of all the routes that you are going to merge. |
Before you start merging there are some important points you will need to consider and there may be some preparation work that will have to be performed.
Identify...
|
Common Problems (and Their Solutions)
Most route mergers will have problems but most of these problems can be easily fixed. |
Some problems will require you to do a bit (or a lot) of extra work before you can merge two routes into one. But for some problems, the best solution may be to select other routes to merge.
|
|
The most common problem in the "impossible to fix" category is when both routes have different orientations (N-S and E-W) and you were hoping to join them end-to-end in the same direction to make an even longer route. Once a route has been created its orientation cannot be changed. |
A handy tip for merging two routes with different heights is to create a new route that only contains the extra "in-between" baseboards - no scenery, textures or track are needed. The baseboards on one end will have heights that match those of the base route and the baseboards on the other end will have heights that match those of the to-be-merged route. The merge is performed in two stages:-
|
Selecting and Loading the Routes to Merge
Load the Base Route into Surveyor
Should you load the Route or the Session?
|
Start the Merge Route Tool and select and load the Route to-be-merged with the Base Route.
|
DLC routes cannot be selected for merging |
This will display a "minimap" of the proposed merger (nothing will be merged until after the final step) with some control options.
The Merge Map
The two tabs shown on the left are the:-
|
Move the To-Be-Merged Route into its New Position
|
The Layers Map
Click the Layers Tab to show the layers loaded from the two routes.
A route merge will not proceed until ALL the terrain and layer conflicts have been eliminated. |
In the example shown below two of the layers, one from each route, are using the same name "route-layer". This causes a conflict that must be resolved before the merge can be completed.
There are three simple options for solving this problem:-
Rename one of the conflicting layers. Double click on the layer name to enter a new name. |
|
Delete one of the conflicting layers. Select the layer and click on the Delete icon. |
|
Merge one of the conflicting layers. |
|
|
Steps:
|
|
|
... the conflict has now been resolved. |
Accept or Reject
Once all the conflicts have been resolved, the final step in the merging process can take place.
ACCEPT: Click to accept the merge. This icon will not be clickable unless ALL conflicts have been resolved. | |
REJECT: Click to reject the merge. The merging will be cancelled, no routes will be lost or altered. |